Joe,
I got my mount from CCI about a year ago, and while it
took loonger to get it than Fred had originally told
me, I think that it only took about 2 months.

This was for a Cozy IV, and I was impressed with the
quality.

I know from discussions on the Cozy builders forum
that there has been a 4130 steel shortage in the US
starting about 6 months ago.  I don't know if that is
impacting delivery or not.

A year ago, Fred was real good at responding to email.
It sounds like he may be much busier now.

Steve Brooks
Cozy MKIV
Turbo rotary
--- Joe <jewen@comporium.net> wrote:

MessageHas anyone on this list actually received an
engine mount from CCI?  I am trying to figure out
how to move my project forward in the engine mount
department so I can get into the fun stuff like
exhaust and cooling.  I ordered a mount from CCI in
August last year subsequent to being quoted a 6 week
lead time.  In Novemeber, CCI stated they had one
more to finish before starting on mine, now this
week I am told it will be another 4 to 6 weeks. With respect to delivery, every communication from
CCI has been grossly wrong so I can not belive the
latest 4 to 6 week info is credible.  Does anyone have any business experience with CCI in
the last 6 months that is different than what I have
decsribed?  Has anyone on this list actually ordered
and recieved a mount in the last 6 months?  Should I
wait another 6 weeks or look for another
alternative?

Any info is appreciated.
Joe