Marve,
We are planning to build the three IVP's as a team. Have two tentative
warehouse locations that have the space required; still negotiating the terms
and conditions, but have until about March to get it locked in. W've agreed to
go "fast build" all the way, and at least two of us are hoping to take
sabaticals to work ths so the project doesn't take forever.

Saw in LNL an article where you had devised a rather elaborate jig/blocking
system to install the fuel probe guides in the wings. I have only studied the
construction manuals; haven't seen the actual wings or probes, but couldn't
you have used the tubing used to align the blocks as a mandrel (perhaps with a
bit of tape to bush it out to the right OD) to hold the guides in good
alignment while you secured them?? Please forgive if this is a stupid
question; I'll try to do better in the future.