Oh, it’s
coming; and I’ve learned never to forecast a completion date; just always
say “next year”. Just finishing the details of my custom
cowling; which with all the fitting, filling, flanging, etc. has taken about 3
times longer than I expected. Airframe – including gear retract,
control rigging etc., is essentially complete, engine installation is 95%
complete, electrical about 25%. Still have to do panel, interior/exterior
finish.
My intent back
when I started was to fly cross country for the Centennial Celebration at Kittyhawk.
Having missed that, it will be done when it’s done.
Al